The platform had limited plot space, a constraint to available headroom, a limitation of 15 tonnes to all offshore lifts and no additional power available for increased pump capacity. These constraints prevented the replacement of the existing separator with a larger vessel.

Jord undertook a full design and performance assessment and designed a solution that utilized a two vessel design with a unique gravity flow layout.

  • The bottleneck to production was resolved enabling the platform to attain the required higher production
  • Capital cost was minimized through design of a solution that overcame the significant constraints of plot space, headroom, lift capacity and
  • Disruption to platform production was minimized and client achieved maximized return on investment