

Two of the modules were for a gas turbine generator service. The others serviced gas compressors. The customer needed these in a hurry and sought any and all ideas to achieve this.
Jord decided upon a common plot-space and mechanical design for both services, and met the design duty by using different set points. This enabled early procurement of components and together with some other initiatives, 8 weeks were shaved off the expected delivery program. A common design also aided plant operability and component inter-changeability between the four modules.
Interested in Fluids treatment and conditioning systems?