This turnkey contract with Indonesian Independent Power Producer (IPP) PT Kartanegara Energi Perkasa (KEP) involves the conversion of a 92MW open cycle power plant into a 117MW combined cycle one. The open cycle plant runs off two GE LM6000 gas turbines.
Our task was to convert the power plant into a 2:2:1 configuration by adding two un-fired, dual pressure, natural circulation HRSG’s and one Siemens SST 300 steam turbine.
Auxiliary plant included in the scope comprised a sea water cooling system using a cooling tower, reverse osmosis and mixed beds for water treatment and demineralising, a condensate and feedwater system, electrical equipment for HV, MV and LV DC circuits and a UPS/DCS system.
The two units have reached mechanical completion and are pictured below. Cold commissioning commenced in November 2019. Covid-19 subsequently put a halt to hot commissioning and performance testing. Jord’s service team remains on stand-by to carry out this work with our customer once conditions on site are more favourable.